The morning of Day 4 was largely spent installing a lighted ceiling fan in son #1's bedroom, which has nothing to do with the bathroom remodel, really, but since the contractor was already here and had to wait for the cement base of the shower to cure anyway, the ceiling fan went in.

This job required access from the attic which involved moving around a bunch of stuff we have stored up there and then removing the plywood flooring and blown-in insulation in the spot above where the fan was installed.  It was hot hot hot in the attic ... about 150 F, so the contractor worked as fast as possible while up there.  The fan is installed and wonderful!  (Should I confess that we purchased this ceiling fan more than a year ago and are just now getting this done?) Son is very happy that his room is much more comfortable and less noisy now.  He no longer needs to run a floor fan.  This ceiling fan is super quiet!


son #1's room
now I want one in the master bedroom!

Progress in the bathroom included:
Tile floor and marble threshold installed


wet saw set up outside


new floor

before grout
after grout
grout will be lighter when fully dry

marble threshold between tile and bedroom carpet

Shower stall cement board installed
Shampoo niche and soap niche installed
The niches are tile ready inserts with appropriate water seal.  These are made to fit perfectly between standard framing and are anchored into the wall framing 2x4's.
Wall tile arrangement has been measured and marked.  The listello will be installed just above the niches.  The rest of the wall will be 6"x6" tiles which match the floor tiles.  The floor tiles are 12" x 12".




The cement tile ready base is fully cured and ready for the mosaic tiles to be installed.

floor mosaic tile goes in

it looks kind of ultra-sloped and bumpy, but it's not
it's just the photography

the diverter is behind that hole in the right side wall
new cement board in place
wall corner rebuilt and mudded
all the cement board has been mudded and seams are sealed

New plumbing!!
Shower has a diverter.  Before there were individual controls for hot and cold.
Sink vanity has two new replacement shut-off valves.
Toilet has a new replacement shut-off valve.
Shower has two new shut-off valves. (it had no shut-off valves at all before)

So sparkly!


new toilet valve

new sink valves



new shower shut off valves

Now we are at the end of day 5.  I'm feeling great, like this will be done in a couple days; for sure by the end of the week and I will be enjoying my new bathroom by the weekend.  Very happy.